April 6, 2009: Pursuant to 30 V.S.A 8093(a), The following is a notification of VELCO's
Irasburg to St. Johnsbury fiber project. The Project will be located at the
Irasburg substation. The Project consists of installing a 72 fiber ALL
Dielectric Self Supporting (ADSS) cable on the transmission structures,
which will connect these two adjacent substations. VELCO plans to commence
this project in June, 2009.
See: Velco Projects
Under Act 131 - 8093, Notification by Utility requires that utility companies notify the VTA of planned projects. The reason for this is that it is sometimes more efficient to allow other service providers to do work at the same time that the utility is working in an area. Please check this Service Provider section of the website regularly to keep up to date on projects that may be happing in your service areas.
See: Velco Projects
VELCO's letter of notification as required by 30 VSA #8093(a) for installation of fiber between VELCO's West Rutland and Blissville substations.
See: West Rutland - Blissville