January 2012 Vermont FiberConnect Status Summary
| Description | Approx 800 mile fiber optic network serving last mile broadband and cellular service providers and approx. 340 community anchor institutions |
| Due date or estimated completion | 6/30/2013 |
| Geographic area | Rutland, Bennington, Windham, Windsor, Orange, Washington, and Caledonia Counties |
| Project status | In pre-construction |
| Dollars spent or disbursed as of 12/31/11 | $6,134,864 |
| Dollars encumbered - total | $35,943,681 |